Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.2 hours per unit
1.6 hours per unit
1.0 hour per unit
1.4 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
The institute of Electronics and Communications Engineers of the Philippines (IECEP) is planning to put up its own building. Two proposals being considered are:A. The construction of the building now to cost P 400,000B. The construction of a smaller building now to cost P300,000 and at the end of 5 years, an extension to be added to cost P 200,000.By how much is proposal B more economical than proposal A if interest rate is 20% and depreciation to be neglected?

P 19,624.49
P 19,518.03
P 19,423.69
P 19,122.15

ANSWER DOWNLOAD EXAMIANS APP