Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.4 hours per unit
1.6 hours per unit
1.2 hours per unit
1.0 hour per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Which is true about partnership?

Its capitalization must be equal for each partner.
It has a perpetual life.
It will be dissolved if one of the partners ceases to be connected with the partnership.
It can be handed down from one generation of partners to another.

ANSWER DOWNLOAD EXAMIANS APP