Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.0 hour per unit
1.6 hours per unit
1.4 hours per unit
1.2 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Which is true about corporation?

Its life is dependent on the lives of the incorporators.
It is worse type of business organization.
The minimum number of incorporators to start a corporation is three.
The stock holders of the corporation are only liable to the extent of their investments.

ANSWER DOWNLOAD EXAMIANS APP