Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.6 hours per unit
1.4 hours per unit
1.0 hour per unit
1.2 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Liquidity ratios are used:

To measure a firm’s ability to meet short-cut obligations
To compare short term obligations to short-term resources available to meet these obligations
To obtain much insight into the present cash solvency of the firm and the firm
All of these

ANSWER DOWNLOAD EXAMIANS APP