Industrial Engineering and Production Management PERT/CPM, techniques can be used for following applications Maintenance jobs Once through project All of these Research and development Maintenance jobs Once through project All of these Research and development ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The basic difference between PERT and CPM is that PERT deals with events and CPM with activities Critical path is determined in PERT only Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM PERT deals with events and CPM with activities Critical path is determined in PERT only Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management M.T.M. is used to All of these Develop effective methods in advance of the beginning of production Establish time standards Improve existing methods All of these Develop effective methods in advance of the beginning of production Establish time standards Improve existing methods ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In perpetual inventory control, the material is checked as it reaches its Maximum value Middle value Minimum value Average value Maximum value Middle value Minimum value Average value ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to All of these Plan and schedule of production Formulate a proper incentive scheme Estimate the selling prices and delivery dates All of these Plan and schedule of production Formulate a proper incentive scheme Estimate the selling prices and delivery dates ANSWER DOWNLOAD EXAMIANS APP