MGVCL Exam Paper (30-07-2021 Shift 2)
In a test by Murray loop for ground fault on 600 m of cable having a resistance of 1.5 Ω/km, the faulty cable is looped with a sound cable of the same length and area of cross section. If the ratio of the other two arms of the testing network at balance is 3 : 1, find the distance of the fault from the testing end of cables.

100 m
200 m
300 m
400 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A 3-phase motor load has a p.f. of 0.397 lagging. The two wattmeter method used to measure power show the input as 30 kW. Find the reading on each wattmeter.

W1 = 5 kW and W2 = 25 kW
W1 = -5 kW and W2 = 35 kW
W1 = -10 kW and W2 = 40 kW
W1 = 10 kW and W2 = 20 kW

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Interposing current-transformer (CT) is used in differential protection of a transformer to

match the standard ratio of CTs used on both sides of the transformer winding
minimize the effect of saturation of the main CTs
limit the main CT secondary current
increase the sensitivity of the relay

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
____are long-term (hours-long) voltage sags caused by system overload.

Brownouts
Voltage surges
Voltage dips
Black outs

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP