MGVCL Exam Paper (30-07-2021 Shift 2)
In a 3-phase, 4-wire, 400/230 V system, a lamp (L1) of 100 W is connected to one phase and neutral and a lamp (L2) of 150 W is connected to the second pahse and neutral. If the neutral wire is disconnected accidently, then

both 100 W lamp (L1) and 150 W lamp (L2) becomes brighter
100 W lamp (L1) becomes brighter and 150 W lamp (L2) becomes dim
both 100 W lamp (L1) and 150 W lamp (L2) becomes dim
100 W lamp (L1) becomes dim and 150 W lamp (L2) becomes brighter

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
____are long-term (hours-long) voltage sags caused by system overload.

Brownouts
Black outs
Voltage dips
Voltage surges

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

5 and 3
6 and 3
3 and 5
3 and 6