Irrigation Engineering If the optimum depth of kor watering for a crop is 15.12 cm, the outlet factor for the crop for four week period in hectares per cumec, is 1700 1600 1400 1500 1700 1600 1400 1500 ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering A 6 hours storm had 4 cm of rainfall and the resulting runoff was 2 cm. If<="" div=""> 9.0 cm 6.0 cm 7.5 cm 4.5 cm 9.0 cm 6.0 cm 7.5 cm 4.5 cm ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The unit hydrograph due to a storm may be obtained by dividing the ordinates of the direct runoff hydrograph by total rainfall None of these period of storm direct runoff volume total rainfall None of these period of storm direct runoff volume ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If the R.L’s of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be superpassage syphon aqueduct syphon aqueduct superpassage syphon aqueduct syphon aqueduct ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Effective precipitation for a crop may be defined as Total precipitation minus the loss due to infiltration Total precipitation minus the loss due to evaporation Available water stored in soil within root zone of the crop Total precipitation during the crop period Total precipitation minus the loss due to infiltration Total precipitation minus the loss due to evaporation Available water stored in soil within root zone of the crop Total precipitation during the crop period ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The structure constructed to allow drainage water to flow under pressure through an inverted syphon below a canal, is called Syphon aqueduct Super passage Syphon Super-aqueduct Syphon aqueduct Super passage Syphon Super-aqueduct ANSWER DOWNLOAD EXAMIANS APP