Irrigation Engineering If it rains between 2 P.M. and 3 P.M. and the entire basin area just starts contributing water at 3 P.M. to the outlet, then time of concentration will be 30 minutes 15 minutes 60 minutes 20 minutes 30 minutes 15 minutes 60 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The drainage water intercepting the canal can be disposed of by passing the canal below the drainage in aqueduct and syphon aqueduct super passage and canal syphon aqueduct and super passage level crossing aqueduct and syphon aqueduct super passage and canal syphon aqueduct and super passage level crossing ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering When surface of transpiration is submerged under water, then potential evapotranspiration is equal to evapotranspiration much less than evapotranspiration much more than evapotranspiration equal to or less than evapotranspi-ration equal to evapotranspiration much less than evapotranspiration much more than evapotranspiration equal to or less than evapotranspi-ration ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be 1 – (0.9)°l0 1/(1+ 0.9010) 1 + (0.9)010 1/(1-0.9°10) 1 – (0.9)°l0 1/(1+ 0.9010) 1 + (0.9)010 1/(1-0.9°10) ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Main purpose of mean water training for rivers is Flood control To provide sufficient depth of water in navigable channels, during low water periods All of these To preserve the channel in good shape by efficient disposal of suspended and bed load Flood control To provide sufficient depth of water in navigable channels, during low water periods All of these To preserve the channel in good shape by efficient disposal of suspended and bed load ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering A counter berm is A horizontal benching provided on the outside slope A vertical benching provided on the inner edge of the bank A vertical benching provided on the outer edge of the bank A horizontal benching provided on the inside slope A horizontal benching provided on the outside slope A vertical benching provided on the inner edge of the bank A vertical benching provided on the outer edge of the bank A horizontal benching provided on the inside slope ANSWER DOWNLOAD EXAMIANS APP