DGVCL Exam Paper (11-12-2011) If a 5 A fuse is blown frequently in a house lighting circuit, it is required to Check the load Insert a fuse of higher voltage rating Insert a fuse of higher current rating Reduce the load Check the load Insert a fuse of higher voltage rating Insert a fuse of higher current rating Reduce the load ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) Different computers are connected to a LAN by a cable and a Interface card Modem Telephone line Special wires Interface card Modem Telephone line Special wires ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) If the voltage at the two ends of a line are 132 kV, and its reactance is 40 Ω, the stability limit of the line is 251.5 MW 217.8 MW 500 MW 435.6 MW 251.5 MW 217.8 MW 500 MW 435.6 MW ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) If the fault current is 2000 A, the relay plug setting is 50% and the CT ratio is 400/5, the plug setting multiple will be 25 10 15 50 25 10 15 50 ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) The efficiency of a transformer at full load, 0.8 p.f. lag is 90%. Its efficiency at full load, 0.8 p.f. lead will be 90 % 80 % Less than 90% More than 90% 90 % 80 % Less than 90% More than 90% ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Efficiency= output power/input powerefficiency = (v*i*cosφ)/((v*i*cosφ)+(x² Pc)+(Pi)) x=fractional part of full load
DGVCL Exam Paper (11-12-2011) The insulation coordination for UHV lines (above 500 kV) is done based on Lightning and switching surges Lightning surges Switching surges Voltage level of the line Lightning and switching surges Lightning surges Switching surges Voltage level of the line ANSWER DOWNLOAD EXAMIANS APP