GETCO Exam Paper (11-06-2017) For the protection of power system against travelling waves, we use overhead ground wires earthing screens surge diverters None of these overhead ground wires earthing screens surge diverters None of these ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Fiber-optic cables are used in power system applications mainly for all SCADA communication between power station and substation communication between power station and load control centre all SCADA communication between power station and substation communication between power station and load control centre ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) As the size of a thermal generating unit increases, the capital cost per kW of installed capacity may increase of decrease increases decreases remain the same may increase of decrease increases decreases remain the same ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) The charging current in the cables lags the voltage by 180˚ leads the voltage by 90˚ lags the voltage by 90˚ leads the voltage by 180˚ lags the voltage by 180˚ leads the voltage by 90˚ lags the voltage by 90˚ leads the voltage by 180˚ ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) On which of the following cycles does a modern steam power plant work? Rankine cycle Bell-Coleman cycle Carnot cycle Otto Cycle Rankine cycle Bell-Coleman cycle Carnot cycle Otto Cycle ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) By increasing the transmission voltage to double of its original value the same power can be dispatched double the original value equal to original value one fourth of original value half the original value double the original value equal to original value one fourth of original value half the original value ANSWER DOWNLOAD EXAMIANS APP