Irrigation Engineering For diversion of flood water of rivers, the type of canal constructed, is Canal Inundation canal Perennial canal Ridge canal Canal Inundation canal Perennial canal Ridge canal ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The ratio of the average load to the installed capacity of the plant whose reserve capacity is zero will be equal to Both load and plant factor Utilization factor Plant factor Load factor Both load and plant factor Utilization factor Plant factor Load factor ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Under the same conditions, which of the following shapes of water surface will give the highest rate of evaporation ? concave water surface convex water surface flat water surface independent of shape of water surface concave water surface convex water surface flat water surface independent of shape of water surface ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The crest level of a canal diversion head work, depends upon Discharge perimeters Pond level All listed here F.S.L. of the canal Discharge perimeters Pond level All listed here F.S.L. of the canal ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If the demand line drawn from a ridge in a flow mass curve does not intersect the curve again, it indicates that reservoir was not full at the beginning None of these demand cannot be met by inflow both (A) and (B) reservoir was not full at the beginning None of these demand cannot be met by inflow both (A) and (B) ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If there are two canals taking off from each flank of a river, then there will be one divide wall and one undersluice two divide walls and two undersluices one divide wall and two undersluices two divide walls and one undersluice one divide wall and one undersluice two divide walls and two undersluices one divide wall and two undersluices two divide walls and one undersluice ANSWER DOWNLOAD EXAMIANS APP