Industrial Engineering and Production Management
Dispatching

Is concerned with the starting of processes
Prescribes the sequence of operations to be followed
Regulates the progress of job through various processes
Determines the programme for the operations

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is negative

It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project
All of these

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
In order that linear programming techniques provide valid results

Either (A) or (B)
Relations between factors must be linear (negative)
Relations between factors must be linear (positive)
Only one factor should change at a time, others remaining constant