Industrial Engineering and Production Management
Dispatching

Regulates the progress of job through various processes
Prescribes the sequence of operations to be followed
Is concerned with the starting of processes
Determines the programme for the operations

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
A big advantage of PERT over Gantt charts is that in the former case

Early start and late finish of an activity are clearly marked
Activity times are clear
Activities and events are clearly shown
Interrelationship among activities is clearly shown

ANSWER DOWNLOAD EXAMIANS APP