MGVCL Exam Paper (30-07-2021 Shift 1)
What is the largest thermal power plant in India?

Vindhyachal Thermal Power Station
Sasan Ultra Mega Power Plant
Mundra Thermal Power Station
Talcher Super Thermal Power Station

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 15 Ω and the resistance of the resistor connected to the sound core was 45 Ω. Calculate the distance of the fault point from the test end.

225 m
450 m
150 m
75 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A balanced delta connected load of 8+j6 Ω per phase is connected to a 415 V, 50 Hz, 3-phase supply lines. If the input power factor is improved to 0.9 by connecting a star connected capacitor bank, then the required kVAR of the bank is

14.98 kVAR
16.98 kVAR
8.98 kVAR
10.98 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A grid interactive solar system:

works only when the grid fails
always receives power from the grid
always supplies power to the grid
supplies power to as well as receives power from the grid as required

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP