Irrigation Engineering Cross regulators in main canals are provided None of these To overflow excessive flow water To increase water head upstream when a main canal is running with low supplies To regulate water supply in the distributaries None of these To overflow excessive flow water To increase water head upstream when a main canal is running with low supplies To regulate water supply in the distributaries ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The ratio of the discharge over a trapezoidal crest to a rectangular crest of Sarda falls of identical parameters, is 1.054 1.064 1.084 1.074 1.054 1.064 1.084 1.074 ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The sensitivity of a rigid module is infinity 1 zero between zero and one infinity 1 zero between zero and one ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If D₁ and D₂ are depths of water upstream and downstream of a hydraulic jump, the loss of head at the jump, is (D₂ - D₁)3/D₁D₂ (D₂ - D₁)3/3D₁D₂ (D₂ - D₁)3/2D₁D₂ (D₂ - D₁)3/4D₁D₂ (D₂ - D₁)3/D₁D₂ (D₂ - D₁)3/3D₁D₂ (D₂ - D₁)3/2D₁D₂ (D₂ - D₁)3/4D₁D₂ ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The uplift pressure on a dam can be controlled byi) constructing cutoff under upstream faceii) constructing drainage channels between the dam and its foundationiii) by pressure grouting in foundationThe corret answer is only (i) both (i) and (ii) (i), (ii) and (iii) both (i) and (iii) only (i) both (i) and (ii) (i), (ii) and (iii) both (i) and (iii) ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The rainfall on five successive days were measured as 100 mm, 80 mm, 60 mm, 40 mm and 20 mm respectively. If the infiltration index or the storm loss rate for the catchment area is earlier estimated as 50 mm/day, the total surface run off will be 140 mm 50 mm 60 mm 90 mm 140 mm 50 mm 60 mm 90 mm ANSWER DOWNLOAD EXAMIANS APP