Soil Mechanics and Foundation
Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is

12 months
6 months
3 months
24 months

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
If the water table rises upto ground surface, then the

total stress is increased due to decrease in pore water pressure but effective stress does not change
effective stress is reduced due to increase in pore water pressure only but total stress does not change
effective stress is reduced due to decrease in total stress only but pore water pressure does not change
total stress is reduced due to increase in pore water pressure only but effective stress does not change

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
The ultimate consolidation settlement of a structure resting on a soil

Decreases with the decrease in the plastic limit
Increases with the decrease in the porosity of the soil
Increases with the increase in the initial voids ratio
Decreases with the increase in the initial voids ratio

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
Quick sand is a

flow condition occurring in cohesive soils
flow condition occurring in both cohesive and cohesionless soils
type of sand
flow condition occurring in cohesionless soils