An air blast C.B. is usually employed for _____ duty

short
repeated
intermittent
instantaneous

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (30-11-2008)
A CB under normal conditions, should be inspected once in

a week
a month
3 or 6 months
5 years

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (30-11-2008)
The voltage regulation of a transformer at full load and 0.8 power factor lagging is 2.5%. The voltage regulation at full load, 0.8 power factor leading will be

0.01
-2.5%
zero
2.5%

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (30-11-2008)
The number of pilot wires required for protecting 3-phase transmission lines using Translay System of protection is

6
3
2
4

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (30-11-2008)
Transfer of power between two power systems takes place with power flowing from the system with the

Greater leading power angle
Lagging power angle
Higher input current
Higher voltage level

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (30-11-2008)
If the fault occurs near the relay, the V/I ratio will be _____ that of if the fault occurs away from the relay.

equal to
none of these
lower than
higher than

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON GETCO Exam Paper (30-11-2008)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑