Power Systems A power station has a maximum demand of 15 MW. The plant capacity is 20 MW. Find the reserve capacity of the plant? 20 MW 5 MW 15 MW 10 MW 20 MW 5 MW 15 MW 10 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following is/are the disadvantages of phase modifiers? Initial cost of synchronous phase modifier is higher It requires more maintenance because of running equipment All of these It consumes both active and reactive power Initial cost of synchronous phase modifier is higher It requires more maintenance because of running equipment All of these It consumes both active and reactive power ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which power plant cannot have single unit of 100 MW capacity Steam power plant. Hydro electric power plant. Nuclear power plant. Diesel engine plant. Steam power plant. Hydro electric power plant. Nuclear power plant. Diesel engine plant. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Reheat cycle in thermal power plant is used to utilize heat of flue gases. increase thermal efficiency. reduce loss of heat. improve condenser performance. utilize heat of flue gases. increase thermal efficiency. reduce loss of heat. improve condenser performance. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line has surge impedance of 400 Ω, operating at Vs = Vr = 400 kV line is compensated with a shunt capacitance of 30%. Find the surge impedance loading with compensation? 456 MW 478 MW 386 MW 400 MW 456 MW 478 MW 386 MW 400 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following rotor is used in thermal power plants? squirrel cage rotor cylindrical rotor salient pole rotor either of these squirrel cage rotor cylindrical rotor salient pole rotor either of these ANSWER DOWNLOAD EXAMIANS APP