MGVCL Exam Paper (30-07-2021 Shift 3)
The purpose of ____ is to check the ability of the circuit breaker to withstand the overvoltages at power frequency as well as undesired value of voltage during lightning and other discharge phenomenon.

short circuit test
synthetic test
routine test
dielectric test

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
The short circuit current of a solar cell is

constant and not affected by radiation
directly proportional to radiation intensity
changes logarithmically with radiation
inversely proportional to radiation intensity

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which of the following statements are correct?
(i) Advanced metering infrastructure (AMI) is typically more automated and allows real- time, on-demand interrogations with metering endpoints.
(ii) An Automated Meter Reading (AMR) device only communicates from the customer to the energy supplier.
(iii) AMR meters only provide kWh information and possible peak kW demand for the month.

(i) and (ii) only
(i), (ii) and (iii)
(ii) and (iii) only
(i) and (iii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP