Irrigation Engineering A divide wall is provided Parallel to the axis of weir and upstream of it At an inclination to the axis of weir Parallel to the axis of weir and downstream of it At right angle to the axis of weir Parallel to the axis of weir and upstream of it At an inclination to the axis of weir Parallel to the axis of weir and downstream of it At right angle to the axis of weir ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Dimensions of coefficient of transmissibility are rvfL’T”1 M° L2 T1 M’LV M°L°T° rvfL’T”1 M° L2 T1 M’LV M°L°T° ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering For the design of major hydraulic structures on the canals, the method generally preferred to, is based on Khosla's method of independent variables The relaxation method Electrical analogy method Bligh's theory Khosla's method of independent variables The relaxation method Electrical analogy method Bligh's theory ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The minimum size of stone that will remain at rest in a channel of longitudinal slope S and hydraulic mean depth R is given by 11RS 4RS 7RS 15 RS 11RS 4RS 7RS 15 RS ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The maximum permissible eccentricity for no tension at the base of a gravity dam is B/2 B/3 B/6 B/4 B/2 B/3 B/6 B/4 ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The uplift pressure on a dam can be controlled by i) constructing cutoff under upstream face ii) constructing drainage channels bet-ween the dam and its foundation iii) by pressure grouting in foundation The corret answer is both (i) and (iii) both (i) and (ii) (i), (ii) and (iii) only (i) both (i) and (iii) both (i) and (ii) (i), (ii) and (iii) only (i) ANSWER DOWNLOAD EXAMIANS APP