Chemical Engineering Plant Economics Which of the following is not a component of the working capital for a chemical process plant? Product inventory Storage facilities In-process inventory Minimum cash reserve Product inventory Storage facilities In-process inventory Minimum cash reserve ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Which of the following is the cheaptest material of construction for the storage of sodium hydroxide upto a concentration of 75%? Copper Plain carbon steel Stainless steel Nickel Copper Plain carbon steel Stainless steel Nickel ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics The payback method for the measurement of return on investment Underemphasises liquidity Takes into account the cash inflows after the recovery of investments Gives a correct picture of profitability Does not measure the discounted rate of return Underemphasises liquidity Takes into account the cash inflows after the recovery of investments Gives a correct picture of profitability Does not measure the discounted rate of return ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Depreciation Is the unavoidable loss in the value of the plant, equipment and materials with lapse in time Costs (on annual basis) are constant when the straight line method is used for its determination All of these Does figure in the calculation of income tax liability on cash flows from an investment Is the unavoidable loss in the value of the plant, equipment and materials with lapse in time Costs (on annual basis) are constant when the straight line method is used for its determination All of these Does figure in the calculation of income tax liability on cash flows from an investment ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics The total investment in a project is Rs. 10 lakhs and the annual profit is 1.5 lakhs. If the project life is 10 years, then the simple rate of return on investment is 10% 1.5% 15% 150% 10% 1.5% 15% 150% ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics The amount of simple interest during 'n' interest period is (where, i = interest rate based on the length of one interest period, p = principal) P(1 + i)n P(1 + i.n) P.i.n. P(1 - i.n) P(1 + i)n P(1 + i.n) P.i.n. P(1 - i.n) ANSWER DOWNLOAD EXAMIANS APP