Water Supply Engineering When the reduced level of the water source is higher than the reduced level of the consumer's place, water is generally supplied Both (A) and (B) By gravitational system All listed here By pumping system Both (A) and (B) By gravitational system All listed here By pumping system ANSWER DOWNLOAD EXAMIANS APP
Water Supply Engineering In slow sland filters, the turbidity of raw water can be removed only up to 75 mg/litre 60 mg/litre 100 gm/litre 150 mg/litre 75 mg/litre 60 mg/litre 100 gm/litre 150 mg/litre ANSWER DOWNLOAD EXAMIANS APP
Water Supply Engineering The specific retention is least in case of Clay Coarse gravel. Silt Sand Clay Coarse gravel. Silt Sand ANSWER DOWNLOAD EXAMIANS APP
Water Supply Engineering For determining the velocity of flow of underground water, the most commonly used non-empirical formula is Lacy’s formula Hazen’s formula Darcy’s formula Slichter’s formula Lacy’s formula Hazen’s formula Darcy’s formula Slichter’s formula ANSWER DOWNLOAD EXAMIANS APP
Water Supply Engineering As per IS : 1172-1963, water required per head per day for average domestic purposes, is 65 litres 135 litres 105 litres 85 litres 65 litres 135 litres 105 litres 85 litres ANSWER DOWNLOAD EXAMIANS APP
Water Supply Engineering The R.L. of ground water table on the sides of a valley is 1505 m whereas R.L. of the stream water is 1475 m. If 60° slope consists of pervious soil between R.L. 1485 m to 1500 m, the gravity spring may be expected at the point of reduced level 1485 m 1505 m 1475 m 1500 m 1485 m 1505 m 1475 m 1500 m ANSWER DOWNLOAD EXAMIANS APP