Economics of Power Generation When the plant restors to load shedding it can be conclucted that Diversity factor is zero Daily load factor is unity Peak demand is more than the installed capacity Plant is under repairs Diversity factor is zero Daily load factor is unity Peak demand is more than the installed capacity Plant is under repairs ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation The depreciation charges in diminishing value method are Heavy in early years Heavy in later years Same in all years Light in early years Heavy in early years Heavy in later years Same in all years Light in early years ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Which plant can never have 100 percent load factor? Nuclear power plant Base load plant Hydroelectric plant Peak load plant Nuclear power plant Base load plant Hydroelectric plant Peak load plant ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation The expected useful life of an hydroelectric power station is around 30 years 60 years 15 years 100 years 30 years 60 years 15 years 100 years ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Annual depreciation cost is calculated by None of the listed here Both sinking fund and straight line method Straight line method Sinking fund method None of the listed here Both sinking fund and straight line method Straight line method Sinking fund method ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Which of the following is not a method for estimating depreciation charges? Halsey Diminishing value method Straight line method Sinking fund method Halsey Diminishing value method Straight line method Sinking fund method ANSWER DOWNLOAD EXAMIANS APP