Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

All of these
To compute target estimate for the owner while drawing and specifications are in initial stage
To have a check on a definitive cost estimate
To check quotations from contractors and/or sub-contractors

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
The institute of Electronics and Communications Engineers of the Philippines (IECEP) is planning to put up its own building. Two proposals being considered are:A. The construction of the building now to cost P 400,000B. The construction of a smaller building now to cost P300,000 and at the end of 5 years, an extension to be added to cost P 200,000.By how much is proposal B more economical than proposal A if interest rate is 20% and depreciation to be neglected?

P 19,518.03
P 19,423.69
P 19,122.15
P 19,624.49

ANSWER DOWNLOAD EXAMIANS APP