Power Systems To improve the efficiency of thermal power plant ________________ is placed between boiler and turbine. economizer. ash handling point. superheater. air preheater. economizer. ash handling point. superheater. air preheater. ANSWER DOWNLOAD EXAMIANS APP
Power Systems For load flow studies, What are the quantities specified at load bus are V and δ δ and Q P and V P and Q V and δ δ and Q P and V P and Q ANSWER DOWNLOAD EXAMIANS APP
Power Systems If, for a given alternator in economic operation mode, the incremental cost is given by (0.012 P + 8) Rs/MWh, dPL/dP = 0.2 and plant λ = 25, then power generation is 1250 MW 1500 MW 1000 MW 750 MW 1250 MW 1500 MW 1000 MW 750 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Positive, negative and zero sequence impedances of line are 2,2 and 5 pu respectively. Find self and mutual impedances respectively? 2 and 5 pu 1 and 3 pu 3 and 1 pu 2 and 2 pu 2 and 5 pu 1 and 3 pu 3 and 1 pu 2 and 2 pu ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line has impedance of (0.005 + j0.05) pu. Find the line at which maximum value of negative DC off set current is produced, if it is applied with Vm sinωt? 9.68 msec 2.63 msec 1.47 msec 4.68 msec 9.68 msec 2.63 msec 1.47 msec 4.68 msec ANSWER DOWNLOAD EXAMIANS APP
Power Systems Among the following which is not non conventional energy Wind. Tidal. Nuclear. Geothermal. Wind. Tidal. Nuclear. Geothermal. ANSWER DOWNLOAD EXAMIANS APP