DGVCL Exam Paper (12-06-2016)

DGVCL Exam Paper (12-06-2016)
The time of closing the cycle, in modern circuit breakers is

0.001 sec.
0.01 sec.
0.003 sec.
0.1 sec.

ANSWER DOWNLOAD EXAMIANS APP

DGVCL Exam Paper (12-06-2016)
For a 66 kV line having span of 200 meters between towers the approximate sag will be 2 m. If the span is double the sag will be:

1 m
8 m
4 m
2 m

ANSWER DOWNLOAD EXAMIANS APP

DGVCL Exam Paper (12-06-2016)
The problematic pollutants in emission of coal based generating plants _____

CO
All of these
SO₂
NOx

ANSWER DOWNLOAD EXAMIANS APP

DGVCL Exam Paper (12-06-2016)
A circuit breaker is designed to protect an electrical circuit from damage caused by :

Over load
Over current
Short circuit
All of these

ANSWER DOWNLOAD EXAMIANS APP

DGVCL Exam Paper (12-06-2016)
Which of the following does not change in a transformer?

Current
All of these
Voltage
Frequency

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

In transformer voltage and current can be raised or lowered.
Frequency remains same
Power and Flux remains almost constant.

DGVCL Exam Paper (12-06-2016)
Which of the following 3-phase connection of a transformer causes interference with the neighbouring communication lines:

Star-Star
Delta-Delta
Delta-Star
Star-Delta

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON DGVCL Exam Paper (12-06-2016)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑