DGVCL Exam Paper (12-06-2016) The relay operating speed depends upon Armature core air gap All of these The rate of flux built up The spring tension Armature core air gap All of these The rate of flux built up The spring tension ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) The problematic pollutants in emission of coal based generating plants _____ SO₂ CO NOx All of these SO₂ CO NOx All of these ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) In a transmission line if booster transformers are to be used, preferred location will be At the receiving end Anywhere in the line At the intermediate point At the sending end At the receiving end Anywhere in the line At the intermediate point At the sending end ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) _____ are used where it is necessary to control a circuit by a low power signal. Transformer None of these Relays Electric Motor Transformer None of these Relays Electric Motor ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) As per Electricity Act, _____ means a process which simultaneously produces two or more forms of useful energy (including electricity). None of these Captive Power Plant Cogeneration Power generation None of these Captive Power Plant Cogeneration Power generation ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) The load of a consumer is generally measured in terms of : Amperes Ampere hour kW Volts Amperes Ampere hour kW Volts ANSWER DOWNLOAD EXAMIANS APP