Environmental Engineering The ratio of 5 day BOD to ultimate BOD is about 43894 43864 43833 1 43894 43864 43833 1 ANSWER DOWNLOAD EXAMIANS APP
Environmental Engineering The process in which the chlorination is done beyond the break point is known as Break point chlorination Super chlorination Post chlorination Pre-chlorination Break point chlorination Super chlorination Post chlorination Pre-chlorination ANSWER DOWNLOAD EXAMIANS APP
Environmental Engineering The main disadvantage of oxidation pond is that None of these BOD removal is very low Large area is required for construction Maintenance and operation cost are high None of these BOD removal is very low Large area is required for construction Maintenance and operation cost are high ANSWER DOWNLOAD EXAMIANS APP
Environmental Engineering The overflow rate for plain sedimentation tanks is about 500 to 750 liters/hour/ m² 1500 to 2000 liters/hour/m² 1250 to 1500 liters/hour/m² 1000 to 1250 liters/hour/ m² 500 to 750 liters/hour/ m² 1500 to 2000 liters/hour/m² 1250 to 1500 liters/hour/m² 1000 to 1250 liters/hour/ m² ANSWER DOWNLOAD EXAMIANS APP
Environmental Engineering The distribution mains are designed for Average daily demand Maximum hourly demand on maximum day Maximum daily demand Maximum hourly demand Average daily demand Maximum hourly demand on maximum day Maximum daily demand Maximum hourly demand ANSWER DOWNLOAD EXAMIANS APP
Environmental Engineering Orthotolidine test is used for determination of Residual chlorine Biochemical oxygen demand Dose of coagulant Dissolved oxygen Residual chlorine Biochemical oxygen demand Dose of coagulant Dissolved oxygen ANSWER DOWNLOAD EXAMIANS APP