DGVCL Exam Paper (12-06-2016) The number of cycles in which a high speed circuit breaker can complete its operation is 10 to 18 20 to 30 40 to 50 3 to 8 10 to 18 20 to 30 40 to 50 3 to 8 ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) The rating of fuse wire is always expressed in _____ Ampere-volts kWh Amperes Ampere-hours Ampere-volts kWh Amperes Ampere-hours ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Equipment :Rating Fuse : AmpereTransformer : kVAAlternator : kVAMotor : kW/HPBattery : ampere-hour
DGVCL Exam Paper (12-06-2016) What would happen if a power transformer designed for operation on 50 Hz (frequency) were connected to a 500 Hz (frequency) source of the same voltage: Current will be too much high Eddy Current and Hysteresis losses will be excessive No effect Transformer may start to smoke and burn Current will be too much high Eddy Current and Hysteresis losses will be excessive No effect Transformer may start to smoke and burn ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Core loss of transformer = Hysteresis loss + eddy current lossHysteresis loss prpotional to feddy current loss prpotional to f².
DGVCL Exam Paper (12-06-2016) The Electricity Act is applicable in _____ All parts of India All the states of India In Gujarat only All parts of India except state of Jammu and Kashmir All parts of India All the states of India In Gujarat only All parts of India except state of Jammu and Kashmir ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) For cost & safety, the outdoor substations are installed for voltages above: 11 kV 60 kV 110 kV 33 kV 11 kV 60 kV 110 kV 33 kV ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) Taskbar is used for Start a program All of above Navigation program Switching between program Start a program All of above Navigation program Switching between program ANSWER DOWNLOAD EXAMIANS APP