GETCO Exam Paper (11-06-2017) The injection of VARs is required to compensate for line losses increase the voltage at the receiving end all get a good voltage profile compensate for line losses increase the voltage at the receiving end all get a good voltage profile ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) In a 3-phase supply, floating neutral is undesirable because it may result in _____ across the load low voltage none high voltage unequal line voltage low voltage none high voltage unequal line voltage ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Effect of temperature rise in overhead lines is to increase both increase the sag and decrease the tension decrease the sag and increase the tension decrease both increase both increase the sag and decrease the tension decrease the sag and increase the tension decrease both ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) If the effect of earth is taken into account, then the capacitance of line to ground increases remains unaltered becomes infinite decreases increases remains unaltered becomes infinite decreases ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) On which of the following cycles does a modern steam power plant work? Carnot cycle Bell-Coleman cycle Otto Cycle Rankine cycle Carnot cycle Bell-Coleman cycle Otto Cycle Rankine cycle ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Fiber-optic cables are used in power system applications mainly for communication between power station and load control centre communication between power station and substation SCADA all communication between power station and load control centre communication between power station and substation SCADA all ANSWER DOWNLOAD EXAMIANS APP