Power Plant Engineering The incomplete combustion is indicated by present of CO CO2 Water vapour O2 CO CO2 Water vapour O2 ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering A nuclear fission is initiated when the critical energy as compared to neutron binding energy of the atoms is More Less There is no such criterion Same More Less There is no such criterion Same ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering The nuclear radiators produced in a reactor which must be shielded are None of these Neutron and gamma rays α, β and γ rays Electrons None of these Neutron and gamma rays α, β and γ rays Electrons ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering The unit of radioactivity is Electron volt MV Curie Electron ampere Electron volt MV Curie Electron ampere ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering The breeding gain in case of thermal breeder reactor as compared to fast breeder reactor is Same Higher Unity Lower Same Higher Unity Lower ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering Plutonium is produced As basic raw material Artificially By neutron irradiation of Uz By neutron irradiation of thorium As basic raw material Artificially By neutron irradiation of Uz By neutron irradiation of thorium ANSWER DOWNLOAD EXAMIANS APP