Power Systems The annual depreciation of hydro power plant is about 15 - 20 %. 0.5 - 1.5 %. 20 - 25 %. 10 - 15 %. 15 - 20 %. 0.5 - 1.5 %. 20 - 25 %. 10 - 15 %. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The zero sequence current of a generator for line to ground fault is j3 pu. Then the current through the neutral during the fault is j3 pu j1 pu j9 pu j6 pu j3 pu j1 pu j9 pu j6 pu ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which material is used in controlling chain reaction in a nuclear reactor Boron. Thorium. Heavy water. Beryllium. Boron. Thorium. Heavy water. Beryllium. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The ratio of reset to pick up current for an induction cup relay is approximately 0.75. 0.99. 1.35. 1.0. 0.75. 0.99. 1.35. 1.0. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Load frequency control is achieved by properly matching the individual machines reactive powers. generator ratings. generated voltages. turbine inputs. reactive powers. generator ratings. generated voltages. turbine inputs. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line is operating under no load has ABCD parameters B = 100∠90° has a phase shift of 0.2 rad, how much shunt reactor is required for compensation of ferranti effect? 2 H 15.9 H 2 mH 15.9 mH 2 H 15.9 H 2 mH 15.9 mH ANSWER DOWNLOAD EXAMIANS APP