Industrial Engineering and Production Management
When slack of an activity is negative

It represents that a programme falls behind schedule and additional resources are required to complete the project in time
It represents a situation where extra resources are available and the completion of project is not delayed
All of these
The activity is critical and any delay in its performance will delay the completion of whole project

ANSWER DOWNLOAD EXAMIANS APP