Industrial Engineering and Production Management
The basic difference between PERT and CPM is that

Critical path is determined in PERT only
Guessed times are used in PERT and evaluated times in CPM
Costs are considered on CPM only and not in PERT
PERT deals with events and CPM with activities

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Travel charts provide

An approximate estimate of the handling which must be done at a particular station
An idea of the flow of materials at various stages
The information for changes required in rearranging material handling equipment
A compact estimate of the handling which must be done between various work sections

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Scheduling

Determines the programme for the operations
Prescribes the sequence of operations to be followed
Is concerned with starting of processes
Regulates the progress of job through various processes

ANSWER DOWNLOAD EXAMIANS APP