Pick up the incorrect statement from the following. A critical ratio scheduling

Establishes the relative priorities among various activities on a common basis
All of the these
Determines the status of each activity
Adjusts automatically changes in activity progress

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
The important file in making a PERT is

An event can't be accomplished until activities leading to it are completed
No activity from any event can be started from preceding event till it is completed
All of the these
Length of arrow has nothing to do with time