Economics of Power Generation power plant cannot have single unit of 100 MW. Steam Hydroelectric Any of the above Nuclear Diesel Steam Hydroelectric Any of the above Nuclear Diesel ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Load shedding is done to Reduce peak demand Run the equipment efficiency Improve power factor Repair the machine Reduce peak demand Run the equipment efficiency Improve power factor Repair the machine ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation ________ is invariably used for peak load None of these Nuclear power plant Steam turbine plant Pumped storage plant None of these Nuclear power plant Steam turbine plant Pumped storage plant ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation In the diminishing value method for calculating depreciation, the annual depreciation charge is independent of The rate of interest Scrap value Initial value of equipment Useful life of equipment The rate of interest Scrap value Initial value of equipment Useful life of equipment ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation A 130 MW generator is usually ____ cooled. Hydrogen Nitrogen Oxygen Air Hydrogen Nitrogen Oxygen Air ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation A low utilization factor for a plant indicates that plant is used for peak load as well as base load plant is used for stand by purpose only plant is under maintenance plant is used for base load only plant is used for peak load as well as base load plant is used for stand by purpose only plant is under maintenance plant is used for base load only ANSWER DOWNLOAD EXAMIANS APP