Industrial Engineering and Production Management Pessimistic time is The average time required for a job The most probable time considering all conditions The maximum time which an activity might require The minimum time in which an activity can possibly be accomplished The average time required for a job The most probable time considering all conditions The maximum time which an activity might require The minimum time in which an activity can possibly be accomplished ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The allowed time for a job equals standard time plus Policy allowance Interference allowance Process allowance Learning allowance Policy allowance Interference allowance Process allowance Learning allowance ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shown Activity times are clear Early start and late finish of an activity are clearly marked Activities and events are clearly shown Interrelationship among activities is clearly shown Activity times are clear Early start and late finish of an activity are clearly marked Activities and events are clearly shown ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The most suitable incentive plan for the maintenance section of an industry will be Profit sharing plans Simplification Group incentive plan Piece rate system Profit sharing plans Simplification Group incentive plan Piece rate system ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.84 0.5 0.95 0.66 0.84 0.5 0.95 0.66 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Earliest finish time can be regarded as Earliest start time + duration of activity Latest finish time + duration of activity Earliest start time duration of activity Latest finish time duration of activity Earliest start time + duration of activity Latest finish time + duration of activity Earliest start time duration of activity Latest finish time duration of activity ANSWER DOWNLOAD EXAMIANS APP