Management Information Systems PERT and CPM are: project evaluation techniques None of these All of these network techniques assignment techniques project evaluation techniques None of these All of these network techniques assignment techniques ANSWER DOWNLOAD EXAMIANS APP
Management Information Systems The latest time that the event can be delayed without delaying the completion of the entire project in PERT chart is: latest pass earliest pass latest allowable time None of these earliest allowable time latest pass earliest pass latest allowable time None of these earliest allowable time ANSWER DOWNLOAD EXAMIANS APP
Management Information Systems Which of the following is not a common configuration used in a DDP system? star tree realtime ring bus star tree realtime ring bus ANSWER DOWNLOAD EXAMIANS APP
Management Information Systems EDP auditing has become popular since 1970 1950 1975 1980 None of these 1970 1950 1975 1980 None of these ANSWER DOWNLOAD EXAMIANS APP
Management Information Systems All mathematical models generally comprise which of the following types of variables; decision variables None of these uncontrollable variables All of these dependent variables decision variables None of these uncontrollable variables All of these dependent variables ANSWER DOWNLOAD EXAMIANS APP
Management Information Systems Personnel Administration Data systems, personnel planning data systems and the payroll system all Ail of the above update the accounts payable file None of these access the inventory file calculate payroll deductions Ail of the above update the accounts payable file None of these access the inventory file calculate payroll deductions ANSWER DOWNLOAD EXAMIANS APP