Generation of Electrical Energy Load factor is generally Less than 1 More than 1 Equal to 1 None of these Less than 1 More than 1 Equal to 1 None of these ANSWER DOWNLOAD EXAMIANS APP
Generation of Electrical Energy Which of the following power plants need the least period for installation? Diesel power plant Hydroelectric plant Nuclear power plant Thermal power plant Diesel power plant Hydroelectric plant Nuclear power plant Thermal power plant ANSWER DOWNLOAD EXAMIANS APP
Generation of Electrical Energy The base load power station supplies load _____ in a day 12 hours 24 hours 16 hours 10 hours 12 hours 24 hours 16 hours 10 hours ANSWER DOWNLOAD EXAMIANS APP
Generation of Electrical Energy Method which is commonly applied for unloading the coal for small power plant is tower cranes lift trucks belt conveyor coal accelerators tower cranes lift trucks belt conveyor coal accelerators ANSWER DOWNLOAD EXAMIANS APP
Generation of Electrical Energy Area under the daily load curve divided by 24 hrs gives Units generated Average load None of these Maximum demand Units generated Average load None of these Maximum demand ANSWER DOWNLOAD EXAMIANS APP
Generation of Electrical Energy The overall efficiency of thermal power plant is equal to Rankine cycle efficiency Carnot cycle efficiency Regenerative cycle efficiency Bioler efficiency × turbine efficiency × generator efficiency Rankine cycle efficiency Carnot cycle efficiency Regenerative cycle efficiency Bioler efficiency × turbine efficiency × generator efficiency ANSWER DOWNLOAD EXAMIANS APP