GETCO Exam Paper (11-06-2017) Lamps in street lighting are all connected in series end-to-end series-parallel parallel series end-to-end series-parallel parallel ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) What time _____ is the train leaving? the train leaves? does the train leave? leaves the train? is the train leaving? the train leaves? does the train leave? leaves the train? ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) SCADA is all real time data acquisition and processing data storing data monitoring and control all real time data acquisition and processing data storing data monitoring and control ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) In hydropower station what is an enlarge body of water just above the intake and used as a regulating reservoir, called Spilways Penstock Reservoir Forebay Spilways Penstock Reservoir Forebay ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) A synchronous condenser is virtually a/an under-excited synchronous motor commutatr motor over-excited synchronous motor induction motor under-excited synchronous motor commutatr motor over-excited synchronous motor induction motor ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Synchronous motor operate at no load with over excitation it behave as synchronous capacitorsupply reactive power at leading power factor
GETCO Exam Paper (11-06-2017) The injection of VARs is required to increase the voltage at the receiving end all compensate for line losses get a good voltage profile increase the voltage at the receiving end all compensate for line losses get a good voltage profile ANSWER DOWNLOAD EXAMIANS APP