RCC Structures Design
In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed

10 mm
20 mm
25 mm
15 mm

ANSWER DOWNLOAD EXAMIANS APP

RCC Structures Design
A pre-stressed concrete member is preferred because

All listed here
Its dimensions are not decided from the diagonal tensile stress
Large size of long beams carrying large shear force need not be adopted
Removal of cracks in the members due to shrinkage

ANSWER DOWNLOAD EXAMIANS APP