Building Maintenance In case of bridge greater than 10.7m in height and which cannot be inspected from beneath due to watery situation the instrument suited for inspection work is? Electrical resistance meter Rain guages Strain gauges Barins snooper vehicle Electrical resistance meter Rain guages Strain gauges Barins snooper vehicle ANSWER DOWNLOAD EXAMIANS APP
Building Maintenance The appearance of glossy patches on the painted surface is called: Running Blistering Flashing Blooming Running Blistering Flashing Blooming ANSWER DOWNLOAD EXAMIANS APP
Building Maintenance Which IS code gives details about termite proofing? IS 5886 IS 5668 IS 6835 IS 6313 IS 5886 IS 5668 IS 6835 IS 6313 ANSWER DOWNLOAD EXAMIANS APP
Building Maintenance In a PSC, the tensioning system may be classified into: 4 3 5 2 4 3 5 2 ANSWER DOWNLOAD EXAMIANS APP
Building Maintenance How many methods of ferro cementing are there? 6 3 2 4 6 3 2 4 ANSWER DOWNLOAD EXAMIANS APP
Building Maintenance A paint normally consists of _________ components. 6 4 5 3 6 4 5 3 ANSWER DOWNLOAD EXAMIANS APP