Irrigation Engineering If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be 1/(1+ 0.9010) 1/(1-0.9°10) 1 – (0.9)°l0 1 + (0.9)010 1/(1+ 0.9010) 1/(1-0.9°10) 1 – (0.9)°l0 1 + (0.9)010 ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering In North Indian Plains, optimum depth of kor watering for wheat, is 13.5 cm 17.5 cm 19.0 cm 23.0 cm 13.5 cm 17.5 cm 19.0 cm 23.0 cm ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Effective precipitation for a crop may be defined as Total precipitation during the crop period Total precipitation minus the loss due to evaporation Total precipitation minus the loss due to infiltration Available water stored in soil within root zone of the crop Total precipitation during the crop period Total precipitation minus the loss due to evaporation Total precipitation minus the loss due to infiltration Available water stored in soil within root zone of the crop ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering In a concrete canal the approximate permissible velocity of water should not exceed 1.5 m/sec 1 m/sec 2 m/sec 0.5 m/sec 1.5 m/sec 1 m/sec 2 m/sec 0.5 m/sec ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Groynes are generally built Inclined downstream up to 30° Inclined up stream up to 30° Perpendicular to the bank All listed here Inclined downstream up to 30° Inclined up stream up to 30° Perpendicular to the bank All listed here ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The net speed under which the turbine reaches its peak efficiency is called rated speed operating speed design speed gross speed rated speed operating speed design speed gross speed ANSWER DOWNLOAD EXAMIANS APP