Engineering Economics If ‘S’ is the future capital accumulated in ‘n’ years at the rate of interest ‘I’ per annum, then present worth is: S (1 + i)1/n None of these S/(1 + i)n S (1 + i)n S (1 + i)1/n None of these S/(1 + i)n S (1 + i)n ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics What is the change in cost per unit variable change called? Incremental cost Supplemental cost Fixed cost Variable cost Incremental cost Supplemental cost Fixed cost Variable cost ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand? 1.2 hours per unit 1.4 hours per unit 1.6 hours per unit 1.0 hour per unit 1.2 hours per unit 1.4 hours per unit 1.6 hours per unit 1.0 hour per unit ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics Which one of the following is not a construction estimate? Conceptual preliminary budget Initial feasibility estimate Definite estimate None of these Conceptual preliminary budget Initial feasibility estimate Definite estimate None of these ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The declining balance method is also known as ______. Constant percentage method Modified sinking fund method Double percentage method Modified SYD method Constant percentage method Modified sinking fund method Double percentage method Modified SYD method ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics Which one of the following questions is relevant to the construction estimates? Did the estimators precisely evaluate site conditions Did the estimators use short cut methods which may be unrealistic in their situation How much money will the contractor's risk, loosing if he were to submit bid on the raw estimate of cost All of these Did the estimators precisely evaluate site conditions Did the estimators use short cut methods which may be unrealistic in their situation How much money will the contractor's risk, loosing if he were to submit bid on the raw estimate of cost All of these ANSWER DOWNLOAD EXAMIANS APP