Irrigation Engineering
If L is total length of a canal in kilometers, P is total perimeter of its lining in metres and C is the cost of lining per square metre, the additional expenditure involved on lining, is

PLC/1000
100 PLC
PL/1000C
PC/100L

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
A divide wall is provided

Parallel to the axis of weir and downstream of it
At an inclination to the axis of weir
At right angle to the axis of weir
Parallel to the axis of weir and upstream of it

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
Infiltration rate is always

equal to or more than the infiltration capacity
equal to or less than the infiltration capacity
less than the infiltration capacity
more than the infiltration capacity

ANSWER DOWNLOAD EXAMIANS APP