Economics of Power Generation For a large installation, it is better to apply Individual correction to large motors Bulk correction to large motors None of the listed here Individual correction to small motors Individual correction to large motors Bulk correction to large motors None of the listed here Individual correction to small motors ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Generating capacity connected to the busbars and ready to take load when switched on is known as Spinning reserve Firm power Hot reserve Cold reserve Spinning reserve Firm power Hot reserve Cold reserve ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation When the power factor of generating station is improved, the cost per unit Increases Remains same None of the listed here Decreases Increases Remains same None of the listed here Decreases ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation A load draws a power of 10 kW at a power factor of 0.707 lagging. The lagging kVAR drawn from the supply will be 15kVAR 20 kVAR 10 kVAR 5 kVAR 15kVAR 20 kVAR 10 kVAR 5 kVAR ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation A consumer has to pay lesser fixed charges in two part tariff maximum demand tariff flat rate tariff any of the above two part tariff maximum demand tariff flat rate tariff any of the above ANSWER DOWNLOAD EXAMIANS APP
Economics of Power Generation Annual depreciation as per straight line method, is calculated by None of these the capital cost minus the salvage value, is divided by the number of years of life increasing a uniform sum of money per annum at stipulated rate of interest the capital cost divided by number of year of life None of these the capital cost minus the salvage value, is divided by the number of years of life increasing a uniform sum of money per annum at stipulated rate of interest the capital cost divided by number of year of life ANSWER DOWNLOAD EXAMIANS APP