GETCO Exam Paper (11-06-2017) Cells are connected in parallel in order to increase the efficiency current capacity voltage rating life of the cells efficiency current capacity voltage rating life of the cells ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Circuit breakers usually operate under None sub-transient state of short circuit current transient state of short circuit current steady short circuit current None sub-transient state of short circuit current transient state of short circuit current steady short circuit current ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Give synonym: Cease Stop Create Begin Dull Stop Create Begin Dull ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) In hydropower station what is an enlarge body of water just above the intake and used as a regulating reservoir, called Forebay Spilways Penstock Reservoir Forebay Spilways Penstock Reservoir ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Steady state stability of a power system is improved by decreasing generator inertia using double circuit line instead of single circuit line reducing fault clearing time single pole switching decreasing generator inertia using double circuit line instead of single circuit line reducing fault clearing time single pole switching ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (11-06-2017) Constant voltage source is active and bilateral passive and unilateral passive and bilateral active and unilateral active and bilateral passive and unilateral passive and bilateral active and unilateral ANSWER DOWNLOAD EXAMIANS APP