DGVCL Exam Paper (12-06-2016) An _____ is a network of electrical components used to supply, transfer and use electric power: All of these Electric power system None of these Electric power All of these Electric power system None of these Electric power ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) Efficiency of a power transformer is of the order of : 1 0.25 0.98 0.5 1 0.25 0.98 0.5 ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) If 3000 kW power is to be transmitted over a distance of 30 km, the desirable transmission voltage will be 33 kV 11 kV 132 kV 66 kV 33 kV 11 kV 132 kV 66 kV ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) The problematic pollutants in emission of coal based generating plants _____ NOx CO All of these SO₂ NOx CO All of these SO₂ ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (12-06-2016) Transformer core is laminated to _____ Reduce all above losses Reduce copper losses Reduce hysteresis loss Reduce eddy current losses Reduce all above losses Reduce copper losses Reduce hysteresis loss Reduce eddy current losses ANSWER EXPLANATION DOWNLOAD EXAMIANS APP To reduce eddy current loss laminations is done.To reduce hysteresis loss good magnetic material (whose specific hysterisis loss is low) is used.
DGVCL Exam Paper (12-06-2016) You should choose Sleep option when The computer is tired after working for the whole day. You finish working and are going to bed. You are leaving for a very short time and want to resume your work shortly. When computer gets hanged frequently. Let it sleep for some time. The computer is tired after working for the whole day. You finish working and are going to bed. You are leaving for a very short time and want to resume your work shortly. When computer gets hanged frequently. Let it sleep for some time. ANSWER DOWNLOAD EXAMIANS APP