Irrigation Engineering According to Lacey, depth of scour in a river depends upon the straightness of the reach. If D is the depth of scour in regime flow in a right angled bend, it is 1.75 D 2.00 D 1.25 D 1.50 D 1.75 D 2.00 D 1.25 D 1.50 D ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If it rains between 2 P.M. and 3 P.M. and the entire basin area just starts contributing water at 3 P.M. to the outlet, then time of concentration will be 30 minutes 60 minutes 15 minutes 20 minutes 30 minutes 60 minutes 15 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The most suitable material for the central impervious core of a zoned embankment type dam is coarse sand clay clay mixed with fine sand silty clay coarse sand clay clay mixed with fine sand silty clay ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Pick up the correct sequence of the part of a canal system from the following Head works-main canal-branch canal-distributary-minor Head work-distributary-branch canal-minor Head works-main canal-branch canal-minor-distributary Heads works-branch canal-main canal distributary, minor Head works-main canal-branch canal-distributary-minor Head work-distributary-branch canal-minor Head works-main canal-branch canal-minor-distributary Heads works-branch canal-main canal distributary, minor ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The total capacity of a reservoir is 25 million cubic metres and dead storage is 5 million cubic metres. If the average volume of sediment deposition is 0.10 million cubic metre per year, then the usefulness of the reservoir will start reducing after 200 years 150 years 250 years 50 years 200 years 150 years 250 years 50 years ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering For smooth entry of water in a canal, the angle between head regulator and water is generally kept 120° 90° 80° 110° 120° 90° 80° 110° ANSWER DOWNLOAD EXAMIANS APP