Power Systems A transmission line is operating under no load has ABCD parameters B = 100∠90° has a phase shift of 0.2 rad, how much shunt reactor is required for compensation of ferranti effect? 2 H 15.9 H 15.9 mH 2 mH 2 H 15.9 H 15.9 mH 2 mH ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following will take least time in starting from cold condition to full load operation Gas turbine plant. Hydro electric power plant. Thermal power plant. Nuclear power plant. Gas turbine plant. Hydro electric power plant. Thermal power plant. Nuclear power plant. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Nuclear power plant are used as intermediate load plants. peak load plants. none of above. base load plants. intermediate load plants. peak load plants. none of above. base load plants. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Find the surge impedance of a line when inductance is 160 mH and capacitance is 1µF? 160 Ω 400 Ω 200 Ω 800 Ω 160 Ω 400 Ω 200 Ω 800 Ω ANSWER DOWNLOAD EXAMIANS APP
Power Systems For 800 MJ stored energy in the rotor at synchronous speed, what is the inertia constant H for a 50 Hz, four pole turbo generator rated 100 MVA, 11 kV? 4 MJ/MVA 8 MJ/MVA 6 MJ/MVA 2 MJ/MVA 4 MJ/MVA 8 MJ/MVA 6 MJ/MVA 2 MJ/MVA ANSWER DOWNLOAD EXAMIANS APP
Power Systems Where air circuit breakers are used? Up to 12 kV. Up to 33 kV. Up to 11 kV. Up to 66 kV. Up to 12 kV. Up to 33 kV. Up to 11 kV. Up to 66 kV. ANSWER DOWNLOAD EXAMIANS APP