Power Systems A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity? 500 MW 1250 MW 750 MW 250 MW 500 MW 1250 MW 750 MW 250 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems In hydroelectric power plants both operating and initial cost are high. both operating and initial cost are low. operating cost is low and initial cost is high. operating cost is high and initial cost is low. both operating and initial cost are high. both operating and initial cost are low. operating cost is low and initial cost is high. operating cost is high and initial cost is low. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A 200 MW capacity generator has a speed regulation of 4% for a frequency drop of 0.05 Hz. Find the power input supplied by the turbine for maintaining constant frequency? 15 MW 20 MW 10 MW 5 MW 15 MW 20 MW 10 MW 5 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Based on the discharge, Kaplan turbine will discharge 1000 lpm >10000 lpm 1000 lpm >10000 lpm ANSWER DOWNLOAD EXAMIANS APP
Power Systems What is the approximate efficiency of a normal thermal power station? 20-25% 30-40% 45-55% 60-70% 20-25% 30-40% 45-55% 60-70% ANSWER DOWNLOAD EXAMIANS APP
Power Systems High capacity generators and motors are of star connected network any of the above star connected with grounding network delta connected network star connected network any of the above star connected with grounding network delta connected network ANSWER DOWNLOAD EXAMIANS APP