Power Systems
A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity?

 750 MW
 500 MW
 1250 MW
 250 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
In hydroelectric power plants

  operating cost is low and initial cost is high.
 both operating and initial cost are low.
 operating cost is high and initial cost is low.
 both operating and initial cost are high.