Engineering Economics
A mathematical expression also known as the present value of annuity of one is called ______.

Load factor
Sinking fund factor
Present worth factor
Demand factor

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
The key to profitable operation for project cost control, is:

To keep the project cost within the cost budget and knowing when and where job costs are deviating
To keep the project cost equal to subsequent construction budget
None of these
To keep the project cost equal to original cost estimate

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
The financial analysis:

Helps to judge the success of the firm's financial plans
All of these
Helps a share holder to compare the expected return on his investment in the firm against the expected return from other alternative investment
Helps a bank to know the financial position of the firm for granting a loan to the firm

ANSWER DOWNLOAD EXAMIANS APP