Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.2 hours per unit
1.6 hours per unit
1.4 hours per unit
1.0 hour per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Under the depletion allowance method in computing depreciation, the depletion charge is equal to either ______ whichever is smaller.

Fixed percentage of gross income or the net taxable income
50% of the fixed percentage of gross income or 50% of the net taxable income
Fixed percentage of gross income or 50% of the net taxable income
50% of the fixed percentage of gross income or the net taxable income

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
In a cash flow series:

Uniform gradient signifies that an income or disbursement changes by the same amount in each interest period
The gradient in the cash flow may be positive or negative
All of these
Either an increase or decrease in the amount of a cash flow is called the gradient

ANSWER DOWNLOAD EXAMIANS APP