A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.4 hours per unit
1.0 hour per unit
1.6 hours per unit
1.2 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Which is true about partnership?

Its capitalization must be equal for each partner.
It will be dissolved if one of the partners ceases to be connected with the partnership.
It has a perpetual life.
It can be handed down from one generation of partners to another.

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
Current ratio is:

(Current assets + loans advances)/Current liabilities
(Current assets + loans)/Current liabilities
Current assets/Current liabilities
None of these