A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.6 hours per unit
1.2 hours per unit
1.0 hour per unit
1.4 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
A leading shoe manufacturer produces a pair of Lebron James signature shoes at a labor cost of P 900.00 a pair and a material cost of P 800.00 a pair. The fixed charges on the business are P 5,000,000 a month and the variable costs are P 400.00 a pair. Royalty to Lebron James is P 1,000 per pair of shoes sold. If the shoes sell at P 5,000 a pair, how many pairs must be produced each month for the manufacturer to break-even?

2632
2712
2.59
2890