Chemical Engineering Plant Economics A balance sheet for an industrial concern shows Only current and fixed assets Only fixed assets The financial condition at any given time Only current assets Only current and fixed assets Only fixed assets The financial condition at any given time Only current assets ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Construction expenses are roughly __________ percent of the total direct cost of the plant. 50 30 10 2 50 30 10 2 ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Direct costs component of the fixed capital consists of Contingencies Labour costs Onsite and offsite costs Raw material costs Contingencies Labour costs Onsite and offsite costs Raw material costs ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics If the interest rate of 10% per period is compounded half yearly, the actual annual return on the principal will be __________ percent. 10 >20 < 20 20 10 >20 < 20 20 ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Which of the following does not come under the sales expenses for a product of a chemical plant? Warehousing Customer service Legal fees Advertising Warehousing Customer service Legal fees Advertising ANSWER DOWNLOAD EXAMIANS APP
Chemical Engineering Plant Economics Chemical engineering plant cost index is used for finding the present cost of a particular chemical plant, if the cost of similar plant at some time in the past is known. The present cost of the plant = original cost x (index value/(index value at original cost was obtained)The most major component of this cost index is Process instruments and control Electrical equipments and material Pumps and compressor Fabricated equipment and machinery Process instruments and control Electrical equipments and material Pumps and compressor Fabricated equipment and machinery ANSWER DOWNLOAD EXAMIANS APP